Cement and steel prices in Colombia: what moves them and how to quote
The price of a bag of cement or a kilo of rebar changes with the brand, the type, the volume, freight to the site and VAT. This guide explains how to compare two quotes and what the official DANE indexes say.
What can influence the price of cement
- Energy. Cement is made by burning limestone and clay at very high temperatures. Fuel and electricity can influence the cost.
- Freight. The farther the site is from the plant, the more transport can weigh.
- Type. General use, high early strength and sulfate resistance are different products. Compare the same designation.
- Volume. A single bag and a full truckload are quoted differently.
What can influence the price of steel
- Scrap and billet. They are inputs of rebar and their price can play a part.
- Exchange rate. It can play a part when the steel or its inputs come from abroad.
- Diameter. The price per kilo can change from one diameter to another.
- Straight, cut or bent. Cutting and bending to the bar schedule are added to the price of the straight bar.
How to compare two quotes
- Same unit. Cement is quoted per bag, or per ton if it is bulk. Steel is quoted per kilo, per ton or per bar of 6 or 12 meters. Convert everything to a price per kilo. The table of masses by diameter is in the rebar guide.
- Same specification. Compare the same type of cement and the same diameter.
- Same scope. Ask whether the price includes VAT (IVA), freight to the site and unloading.
- Total delivered to the site. That is the number to compare. Also check until what date the quote holds.
What the DANE data says
Every month DANE measures with the ICOCED how much the prices of construction inputs change. They are variations of an index.
| Indicator | Figure | Period |
|---|---|---|
| Building construction cost (ICOCED total) | 7.12% annual and −0.13% monthly | September 2026 against September 2025 and against August 2026 |
| Cement as an input | −0.12% annual. It weighs 7.34% of the index | September 2026 against September 2025 |
| Rebar as an input | 8.62% annual. It weighs 7.81% of the index | September 2026 against September 2025 |
| Grey cement shipments to the domestic market | 9,868.3 thousand tons, 3.6% more | January to September 2026 against the same period of 2025 |
| Bagged cement and bulk cement | 5.3% and −0.2% | January to September 2026 against the same period of 2025 |
To track the trend, open the ICOCED page each month and find the rows for cement (cemento) and rebar (acero corrugado) in the inputs sheet of the Excel annex (Anexo 5.3). The Grey Cement Statistics page shows demand.
How to get the real price for your project
Build the list in the Parex quoter with the presentation and the quantity. For example: grey cement 50 kg, 100 bags. You do not need an account to build the list. You see prices when you create your account. The quote shows the price of each material with shipping and taxes included and confirms the delivery date for the site address.
Individuals and builders pay upfront. Construction companies with a registered company name and a NIT (Colombian tax ID) can also apply for credit on 30, 60 or 90-day terms. See cement by the bag or in bulk and rebar, mesh and cut and bent steel. If you are still deciding where to buy, read where to buy construction materials.
Frequently asked questions.
It depends on the type of cement, the brand, the bag weight, the quantity, freight to the site and VAT. To find your price, ask for a quote with your list and the site address.
It depends on the diameter, on whether the bar is straight, cut or bent, on the volume and on freight. Ask for a quote per kilo for each diameter and check how long it is valid.
Energy, transport and demand can all play a part. According to DANE, in September 2026 cement as an input for building construction changed −0.12% against September 2025.
The prices of scrap and billet and the exchange rate can play a part. According to DANE, in September 2026 rebar as an input for building construction rose 8.62% against September 2025.
DANE publishes indexes of variation and states that the ICOCED does not aim to report the value in pesos of each input. The value for your project comes from a quote.
- DANE, Índice de Costos de la Construcción de Edificaciones (ICOCED), boletín técnico de septiembre de 2026, publicado el 30 de octubre de 2026
- DANE, ICOCED, anexos de septiembre de 2026 (Anexo 5.3, insumos), actualizados el 30 de octubre de 2026
- DANE, ICOCED, página de la operación estadística (boletines y anexos de cada mes)
- DANE, Estadísticas de Cemento Gris (ECG), boletín técnico de septiembre de 2026, publicado el 30 de octubre de 2026 (cifras provisionales)
- DANE, Estadísticas de Cemento Gris (ECG), página de la operación estadística